Washington State University Libraries, Manuscripts, Archives, and Special Collections (MASC)
Facilities Planning Department Building File 1960-1984
Archives 185
Table of Contents
- Summary Information
- Organizational History:
- Scope and Content
- Arrangement
- Administrative Information
- Names and Subjects
- Detailed Description of Collection
- Alterations to College Hall, Phase II (Bldg. 4)
- Bohler Gym-Shower & Toilet Room Remodel (Bldg. 11)
- Wilmer-Davis Dining Hall Renovation (Bldg. 30)
- Science Hall - 5th Floor Addition (Bldg. 32)
- Electron Microscope (Science) (Bldg. 32)
- Arts Hall (Murrow East) Remodel, Phase I (Bldg. 33)
- Arts Hall (Murrow) Remodel, Phase II (Bldg. 33)
- Troy Hall Remodel (Bldg. 36)
- Wilson Hall Remodel (Bldg. 40)
- McCoy Hall, South Addition, Phase I (Bldg. 44)
- McCoy Hall, South Addition, Phase II (Bldg. 44)
- McCoy Hall, North Addition (Bldg. 44)
- Compton Union Building Remodel (Bldg. 63)
- Johnson Hall (Bldg. 76)
- Dining Hall Rotunda (Bldg. 80)
- Streit-Perham Halls (Bldg. 81)
- Agricultural Sciences Building, Phase I (Bldg. 99)
- Farm Services Building & Maintenance Shops (Bldg. 103)
- General Services Complex (Bldg. 358)
- Tula Young Hastings Research Farm (Bldg. 404)
- Beef Cattle Breeding Center (Bldg. 404
- Afro American Pavilion (Bldg. 404D)
- Kamiak Apartments (Bldg. 660)
- Steptoe Family Housing (Bldg. 665)
- Graduate Student (McEachern) Residence Hall (Bldg. 805)
- Agricultural Sciences Bldg., Phs. I&II Lands. (Bl. 808)
- Agricultural Sciences Bldg., Ph. II (Bldg. 808)
- English Building (Bldg. 809)
- Experiment Stations
- Sample Drying Building, Prosser
- Feed Plant Facility, Prosser
- Horticulture Materials Storage Building, Prosser
- Miscellaneous Small Projects
- Machine Storage Building, Mt. Vernon
- Lab Remodeling, Mt. Vernon
- Dry Land Research Station, Lind
- Coliseum Parking Structure
- Dog Runs
- East Campus Substation
- Troy Road Completion
- Exterior Concrete Steps
- Small Jobs
- Hourly Rate Contract
- Miscellaneous Small Projects
- Mobile Home Project
- Wilson Mall (later called Terrell Mall)
Summary Information
- Repository
- Washington State University Libraries, Manuscripts, Archives, and Special Collections Manuscripts, Archives, and Special Collections (MASC)
- Title
- Facilities Planning Department Building File
- ID
- Archives 185
- Date [inclusive]
- 1960-1984
- Date [bulk]
- 1969-1975
- Extent
- 11 linear feet of shelf space, 9 containers
- Language
- Collection materials are in English.
- Abstract
- Records consist of correspondence, reports, bidding records, and other documents related to architectural work and construction.
Organizational History:
A University Architect has served as the construction officer of Washington State University from 1911 onward. The modern form of the office dates from 1947, when it became a full-time staffed administrative department. In 1967, the office was renamed as Facilities Planning and later as Facilities Development. It is responsible for the major construction projects of the University.
Scope and Content
The records consist of correspondence, reports, bidding records, and other documents related to architectural work and construction.
The materials in this Archive are restricted to the use of authorized personnel only.
Arrangement
Records of the University Architect/Facilities Planning are arranged according to the building number system that identifies structures owned by Washington State University. The archival arrangement of the record follows the office practice without variance.
Locating records revenant to a specific project or building requires having the building number available.
Administrative Information
Publication Information
Washington State University Libraries, Manuscripts, Archives, and Special Collections (MASC)
http://www.libraries.wsu.edu/masc/
Terrell Library
P.O. Box 645610
Pullman, WA, 99164-5610 USA
509-335-6691
mascref@wsu.edu
Restrictions on Access
The Collection is open for research use.
Acquisition Information
This portion of the University Architect/Facilities Planning building file was transferred to University Archives in 1983 (UA83-09, UA 83-11), 1985 (UA85-47), and 1986 (UA86-03) in accordance with approved records schedules. In 2010, three folders which appear to have been misplaced from this collection prior to processing were added (270A-C).
Processing Information
The records were processed by Leslie J. Tevebaugh in March, 986, and the descriptions were expanded and enhanced by Brenda Jackson in October, 2000.
Names and Subjects
Corporate Name(s)
Creator(s) :
- Washington State University. Department of Facilities Planning--Archives
- Washington State University. University Architect.
Subject(s) :
- Washington State University. Department of Facilities Planning--Records and correspondence
- Washington State University. Buildings--History--Archives
Subject(s)
- College buildings--Washington (State)--Designs and plans
- Washington (State)
- Colleges and Universities
- Architecture
Detailed Description of Collection
Alterations to College Hall, Phase II (Bldg. 4) |
||||
box | folder | |||
Carlson & James, Archs., Correspondence 1968 |
1 | 1 | ||
General Correspondence 1968-1973 |
1 | 2 | ||
S.G. Morin & Son, Correspondence 1968-1969 |
1 | 3 | ||
S.G. Morin & Son, Contract & COs |
1 | 4 | ||
Rejected Bids |
1 | 5 | ||
|
||||
Bohler Gym-Shower & Toilet Room Remodel (Bldg. 11) |
||||
box | folder | |||
General Correspondence 1971-1972 |
1 | 6 | ||
Molander Associates, Archs., Correspondence 1971 |
1 | 7 | ||
Molander Associates, Archs., Contract, Payments, COs |
1 | 8 | ||
C&S Builders, Correspondence 1971-1972 |
1 | 9 | ||
C&S Builders, Contract, Payments, COs |
1 | 10 | ||
Rejected Bids |
1 | 11 | ||
|
||||
Wilmer-Davis Dining Hall Renovation (Bldg. 30) |
||||
box | folder | |||
Budget |
1 | 12 | ||
General Correspondence 1971-1975 |
1 | 13 | ||
Diary-Inspection Reports |
1 | 14 | ||
Inspection Reports |
1 | 15 | ||
James & Hicks, Archs., Correspondence 1971-1972 |
1 | 16 | ||
James & Hicks, Archs., Contract, Payments, COs |
1 | 17 | ||
Vern W. Johnson & Sons, Correspondence 1970-1972 |
1 | 18 | ||
Vern W. Johnson & Sons, Contract, Payments, COs |
1 | 19 | ||
Vern W. Johnson & Sons, Affirmative Action Reports |
1 | 20 | ||
Senna Service, Inc., Correspondence 1970-1972 |
1 | 21 | ||
Senna Service, Inc., Contract, Payments, COs |
1 | 22 | ||
Senna Service, Inc., Affirmative Action Reports |
1 | 23 | ||
Ray Dillon Electric, Contract, Payments, COs |
1 | 24 | ||
Ray Dillon Electric, Affirmative Action Reports |
1 | 25 | ||
Pittsburgh Testing Lab, Concrete Testing |
1 | 26 | ||
General Correspondence 1968-1970 |
1 | 27 | ||
James & Hicks, Archs., Correspondence 1969-1970 |
1 | 28 | ||
Rejected Bids - General |
1 | 29 | ||
Rejected Bids - Mechanical |
1 | 30 | ||
Rejected Bids - Electrical |
1 | 31 | ||
|
||||
Science Hall - 5th Floor Addition (Bldg. 32) |
||||
box | folder | |||
Budget |
1 | 32 | ||
Program |
1 | 33 | ||
Diary Inspection Reports |
1 | 34 | ||
Douglas C. Durkoop, Arch., Corres. 1969-1970 |
1 | 35 | ||
General Correspondence 1969-1970 |
1 | 36 | ||
Douglas C. Durkoop, Arch., Contract, Payments, COs |
1 | 37 | ||
Commercial Builders, Inc., Correspondence 1971-1972 |
1 | 38 | ||
C&S Builders, Contract & COs |
1 | 39 | ||
Rejected Bids |
1 | 40 | ||
|
||||
Electron Microscope (Science) (Bldg. 32) |
||||
box | folder | |||
Budget |
1 | 41 | ||
General Correspondence 1970-1972 |
1 | 42 | ||
Carlson & James, Archs., Correspondence 1970-1971 |
1 | 43 | ||
Carlson & James, Archs., Contract, Payments, COs |
1 | 44 | ||
Commercial Builders, Inc., Correspondence 1971-1972 |
1 | 45 | ||
Commercial Builders, Inc., Contract, Payments, COs |
1 | 46 | ||
Rejected Bids |
1 | 47 | ||
|
||||
Arts Hall (Murrow East) Remodel, Phase I (Bldg. 33) |
||||
box | folder | |||
Budget |
1 | 48 | ||
Cost Estimate, Outline Finish Schedule, Schedule of Areas |
1 | 49 | ||
Program |
1 | 50 | ||
General Correspondence 1968-1970 |
1 | 51 | ||
General Correspondence 1971-1974 |
1 | 52 | ||
DeNeff, Deeble & Barton, Archs., Correspondence 1968-1970 |
1 | 53 | ||
DeNeff, Deeble & Barton, Archs., Correspondence 1970-1971 |
1 | 54 | ||
DeNeff, Deeble & Barton, Archs., Correspondence 1971-1973 |
1 | 55 | ||
DeNeff, Deeble & Barton, Archs., Contract & COs |
1 | 56 | ||
Neil H. Twelker & Assoc., Soils Investigation |
2 | 57 | ||
Warren, Little & Lund, Inc., Correspondence 1970-1972 |
2 | 58 | ||
Warren, Little & Lund, Inc., Contract, Payments, COs |
2 | 59 | ||
Warren, Little & Lund, Inc., Affirmative Action Reports |
2 | 60 | ||
Babbitt Electric, Correspondence 1970-1972 |
2 | 61 | ||
Babbitt Electric, Contract, Payments, COs |
2 | 62 | ||
Babbitt Electric, Affirmative Action Reports |
2 | 63 | ||
Skyline Construction Co., Afffirmative Action Reports |
2 | 64 | ||
Pittsburgh Testing Lab., Concrete Testing |
2 | 65 | ||
Rejected Bids - General |
2 | 66 | ||
Rejected Bids - Mechanical |
2 | 67 | ||
Rejected Bids - Electrical |
2 | 68 | ||
Proposed Communications Building |
2 | 69 | ||
|
||||
Arts Hall (Murrow) Remodel, Phase II (Bldg. 33) |
||||
box | folder | |||
Budget |
2 | 70 | ||
General Correspondence 1970-1971 |
2 | 71 | ||
General Correspondence 1972-1975 |
2 | 72 | ||
DeNeff, Deeble & Barton, Archs., Correspondence 1970-1974 |
2 | 73 | ||
DeNeff, Deeble & Barton, Archs., Contract, Payments, COs |
2 | 74 | ||
Diary Inspection Reports |
2 | 75 | ||
C&S Builders, Inc., Correspondence 1972-1973 |
2 | 76 | ||
C&S Builders, Inc., Affirmative Action Reports |
2 | 77 | ||
C&S Builders, Inc., Contract, Payments, COs |
2 | 78 | ||
Warren, Little & Lund, Inc., Correspondence 1972-1973 |
2 | 79 | ||
Warren, Little & Lund, Inc., Contract, Payments, COs |
2 | 80 | ||
Warren, Little & Lund, Inc., Affirmative Action Reports |
2 | 81 | ||
Kohler Electric, Inc., Correspondence 1972-1973 |
2 | 82 | ||
Kohler Electric, Inc., Contract, Payments, COs |
2 | 83 | ||
Kohler Electric, Inc., Affirmative Action Reports |
2 | 84 | ||
Rejected Bids - General |
2 | 85 | ||
Rejected Bids - Mechanical |
2 | 86 | ||
Rejected Bids - Electrical |
2 | 87 | ||
|
||||
Troy Hall Remodel (Bldg. 36) |
||||
box | folder | |||
Budget |
2 | 88 | ||
Program |
2 | 89 | ||
General Correspondence 1970-1973 |
2 | 90 | ||
Diary Inspection Reports |
2 | 91 | ||
Douglas Durkoop, Arch., Correspondence 1970-1973 |
2 | 92 | ||
Douglas Durkoop, Arch., Site Visit & Monthly Cons. Mtgs. |
2 | 93 | ||
Douglas Durkoop, Arch., Contract, Payments, COs |
2 | 94 | ||
Construction Development Corp., Correspondence 1971-1973 |
2 | 95 | ||
Construction Development Corp., Contract, Payments, COs |
2 | 96 | ||
Construction Development Corp., Affirmative Action Reports |
2 | 97 | ||
Senna Service, Inc., Correspondence 1971-1973 |
2 | 98 | ||
Senna Service, Inc., Contract, Payments, COs |
2 | 99 | ||
Senna Service, Inc., Affirmative Action Reports |
2 | 100 | ||
Intermountain Electric, Inc., Correspondence 1971-1973 |
2 | 101 | ||
Intermountain Electric, Inc., Contract, Payments, COs |
2 | 102 | ||
Rejected Bids - General |
2 | 103 | ||
Rejected Bids - Electrical |
2 | 104 | ||
Rejected Bids - Mechanical |
2 | 105 | ||
|
||||
Wilson Hall Remodel (Bldg. 40) |
||||
box | folder | |||
Budget |
2 | 106 | ||
General Correspondence 1969-1973 |
2 | 107 | ||
Building Program |
2 | 108 | ||
Diary Inspection Reports |
2 | 109 | ||
DeNeff, Deeble & Barton, Archs., Correspondence 1970-1973 |
2 | 110 | ||
DeNeff, Deeble & Barton, Archs., Contract, Payments, COs |
2 | 111 | ||
DeNeff, et al, Archs., Site Visit & Monthly Cons. Mtgs. |
2 | 112 | ||
Halvorson-Berg, Correspondence 1971-1972 |
2 | 113 | ||
Halvorson-Berg, Contract, Payments, COs |
2 | 114 | ||
Halvorson-Berg, Affirmative Action Reports |
2 | 115 | ||
C&S Builders, Contract & COs |
2 | 116 | ||
Warren, Little & Lund, Correspondence 1971-1972 |
2 | 117 | ||
Warren, Little & Lund, Contract, Payments, COs |
2 | 118 | ||
Warren, Little & Lund, Affirmative Action Reports |
2 | 119 | ||
Ray Dillon Electric, Correspondence 1971-1972 |
2 | 120 | ||
Ray Dillon Electric, Contract, Payments, COs |
2 | 121 | ||
Ray Dillon Electric, Affirmative Action Reports |
2 | 122 | ||
Rejected Bids - General |
2 | 123 | ||
Rejected Bids - Mechanical |
2 | 124 | ||
Rejected Bids - Electrical |
2 | 125 | ||
|
||||
McCoy Hall, South Addition, Phase I (Bldg. 44) |
||||
box | folder | |||
Budget |
3 | 126 | ||
General Correspondence 1970-1972 |
3 | 127 | ||
Daily Inspection Reports |
3 | 128 | ||
Culler, Gale, Martell, Ericson, Archs., Corres. 1970-1972 |
3 | 129 | ||
Culler, et al, Archs., Contract, Payments, COs |
3 | 130 | ||
Culler, et al, Archs., Construction Reports |
3 | 131 | ||
C&S Builders, Inc., Correspondence 1970-1972 |
3 | 132 | ||
C&S Builders, Inc., Contract, Payments, COs |
3 | 133 | ||
C&S Builders, Inc., Affirmative Action Reports |
3 | 134 | ||
Pittsburgh Testing Lab., Concrete Testing |
3 | 135 | ||
Rejected Bids |
3 | 136 | ||
|
||||
McCoy Hall, South Addition, Phase II (Bldg. 44) |
||||
box | folder | |||
Budget |
3 | 137 | ||
General Correspondence 1971-1973 |
3 | 138 | ||
Diary Inspection Reports |
3 | 139 | ||
Culler, Gale, Martell, Ericson, Archs., Corres. 1970-1973 |
3 | 140 | ||
Culler, et al, Archs., Contract, Payments, COs |
3 | 141 | ||
S.G. Morin & Son, Correspondence 1972 |
3 | 142 | ||
S.G. Morin & Son, Contract, Payments, COs |
3 | 143 | ||
S.G. Morin & Son, Affirmative Action Reports |
3 | 144 | ||
Rejected Bids |
3 | 145 | ||
|
||||
McCoy Hall, North Addition (Bldg. 44) |
||||
box | folder | |||
Budget |
3 | 146 | ||
Program Statement |
3 | 147 | ||
General Correspondence 1968-1974 |
3 | 148 | ||
Daily Inspection Reports |
3 | 149 | ||
Culler, Gale, Martell, Ericson, Archs., Corres. 1969-1971 |
3 | 150 | ||
Culler, et al, Archs., Contract, Payments, COs |
3 | 151 | ||
Culler, et al, Archs., Construction Reports |
3 | 152 | ||
C&S Builders, Inc., Correspondence 1970-1971 |
3 | 153 | ||
C&S Builders, Inc., Contract, Payments, COs |
3 | 154 | ||
C&S Builders, Inc., Affirmative Action Reports |
3 | 155 | ||
Rejected Bids |
3 | 156 | ||
|
||||
Compton Union Building Remodel (Bldg. 63) |
||||
box | folder | |||
Budget |
3 | 157 | ||
General Correspondence 1960-1970 |
3 | 158 | ||
General Correspondence 1974-1975 |
3 | 159 | ||
Diary Inspection Reports |
3 | 160 | ||
Douglas Durkoop, Arch., Correspondence 1974 |
3 | 161 | ||
Gil Bauer Construction, Correspondence 1974-1975 |
3 | 162 | ||
Gil Bauer Construction, Contract, Payments, COs |
3 | 163 | ||
Rejected Bids |
3 | 164 | ||
|
||||
Johnson Hall (Bldg. 76) |
||||
box | folder | |||
General Correspondence 1969-1972 |
3 | 165 | ||
|
||||
Dining Hall Rotunda (Bldg. 80) |
||||
box | folder | |||
General Correspondence 1965-1972 |
3 | 166 | ||
|
||||
Streit-Perham Halls (Bldg. 81) |
||||
box | folder | |||
Ceiling-Plaster Correspondence 1970 |
3 | 167 | ||
Window & Plaster Problems |
3 | 168 | ||
|
||||
Agricultural Sciences Building, Phase I (Bldg. 99) |
||||
box | folder | |||
Budget |
3 | 169 | ||
Program Statement |
3 | 170 | ||
Room Index |
3 | 171 | ||
General Correspondence 1972-1975 |
3 | 172 | ||
General Correspondence, 7/71-12/71 |
3 | 173 | ||
General Correspondence, 1/71-6/71 |
3 | 174 | ||
General Correspondence 1970 |
3 | 175 | ||
General Correspondence, 4/69-12/69 |
3 | 176 | ||
General Correspondence 1967-3/1969 |
3 | 177 | ||
Lloyd J. Lovegren & Assoc., Correspondence, 9/71-1972 |
3 | 178 | ||
Lloyd J. Lovegren & Assoc., Correspondence, 1/71-8/71 |
3 | 179 | ||
Lloyd J. Lovegren & Assoc., Correspondence, 7/70-12/70 |
4 | 180 | ||
Lloyd J. Lovegren & Assoc., Correspondence, 11/69-6/70 |
4 | 181 | ||
Lloyd J. Lovegren & Assoc., Correspondence, 4/69-10/69 |
4 | 182 | ||
Lloyd J. Lovegren & Assoc., Correspondence, 1/69-3/69 |
4 | 183 | ||
Lloyd J. Lovegren & Assoc., Correspondence 1967-1968 |
4 | 184 | ||
Lloyd J. Lovegren & Assoc., Contract & COs |
4 | 185 | ||
Diary-Inspection Reports 1971 |
4 | 186 | ||
Diary-Inspection Reports 1969-1970 |
4 | 187 | ||
Lloyd J. Lovegren & Assoc., Construction Conference Notes |
4 | 188 | ||
Bouillon, Christofferson & Schairer, Construc. Mtg. Nts. |
4 | 189 | ||
Alfred Brown Co., Correspondence 1969-1972 |
4 | 190 | ||
Alfred Brown Co., Contract, Payments, COs |
4 | 191 | ||
Vern W. Johnson, Correspondence 1969 |
4 | 192 | ||
Vern W. Johnson, Contract, Payments, COs |
4 | 193 | ||
Keying Schedule |
4 | 194 | ||
Western Consultants, Contract & COs |
4 | 195 | ||
Geolabs, Inc., Foundation Investigation |
4 | 196 | ||
Pittsburgh Testing Labs., Concrete Testing |
4 | 197 | ||
W.R. O'Rourke Co., Inc., Correspondence 1969-1972 |
4 | 198 | ||
W.R. O'Rourke Co., Inc., Contract, Payments, COs |
4 | 199 | ||
Babbitt Electric & Refrig., Correspondence 1969-1973 |
4 | 200 | ||
Babbitt Electric & Refrig., Contract, Payments, COs |
4 | 201 | ||
Hamilton Manufacturing Co., Correspondence 1969-1972 |
4 | 202 | ||
Hamilton Manufacturing Co., Contract, Payments, COs |
4 | 203 | ||
Robert W. Chittock, Landscape Arch., Correspondence 1969 |
4 | 204 | ||
Rejected Bids - General |
4 | 205 | ||
Rejected Bids - Mechanical |
4 | 206 | ||
Rejected Bids - Electrical |
4 | 207 | ||
Rejected Bids - Earth Moving |
4 | 208 | ||
Rejected Bids - Lab Equipment |
4 | 209 | ||
Rejected Bids - Landscape |
4 | 210 | ||
|
||||
Farm Services Building & Maintenance Shops (Bldg. 103) |
||||
box | folder | |||
Budget |
4 | 211 | ||
General Correspondence 1967-1969 |
4 | 212 | ||
J.J. Dodgen, Correspondence 1968-1969 |
4 | 213 | ||
J.J. Dodgen, Contract & COs |
4 | 214 | ||
Rejected Bids |
4 | 215 | ||
|
||||
General Services Complex (Bldg. 358) |
||||
box | folder | |||
Budget |
4 | 216 | ||
Program |
4 | 217 | ||
General Correspondence 1967-1972 |
4 | 218 | ||
Victor L. Wulff & Assoc., Correspondence 1968-1970 |
4 | 219 | ||
Victor L. Wulff & Assoc., Contract & COs |
4 | 220 | ||
Victor L. Wulff & Assoc., Job Meetings |
5 | 221 | ||
Vern W. Johnson & Son, Correspondence 1968-1969 |
5 | 222 | ||
Vern W. Johnson & Son, Contract, Payments, COs |
5 | 223 | ||
Concrete Testing |
5 | 224 | ||
Rejected Bids |
5 | 225 | ||
|
||||
Tula Young Hastings Research Farm (Bldg. 404) |
||||
box | folder | |||
Program |
5 | 226 | ||
General Correspondence 1967-1974 |
5 | 227 | ||
Environmental Concern, Inc., Correspondence 1970-1975 |
5 | 228 | ||
Environmental Concern, Inc., Contract, Payments, COs |
5 | 229 | ||
|
||||
Beef Cattle Breeding Center (Bldg. 404 |
||||
box | folder | |||
Budget |
5 | 230 | ||
General Correspondence 1973-1984 |
5 | 231 | ||
General Correspondence 1970-1972 |
5 | 232 | ||
Environmental Concern, Inc., Correspondence 1970-1977 |
5 | 233 | ||
Daily Inspection Reports |
5 | 234 | ||
Environmental Concern, Inc., Contract, Payments, COs |
5 | 235 | ||
Environmental Concern, Inc., Site Visits & Coord. Mtgs. |
5 | 236 | ||
Mountain States Construction, Correspondence 1972-1973 |
5 | 237 | ||
Mountain States Construction, Contract, Payments, COs |
5 | 238 | ||
Mountain States Construction, Affirmative Action Rpts. |
5 | 239 | ||
Randolph Plumbing & Heating Co., Correspondence 1972-1973 |
5 | 240 | ||
Randolph Plumbing & Heating Co., Contract, Payments, COs |
5 | 241 | ||
Power City Electric, Correspondence 1972-1973 |
5 | 242 | ||
Power City Electric, Contract, Payments, COs |
5 | 243 | ||
Power City Electric, Affirmative Action Reports |
5 | 244 | ||
Rejected Bids, General |
5 | 245 | ||
Rejected Bids, Mechanical |
5 | 246 | ||
Rejected Bids, Electrical |
5 | 247 | ||
|
||||
Afro American Pavilion (Bldg. 404D) |
||||
box | folder | |||
Budget |
5 | 248 | ||
Correspondence 1974-1975 |
5 | 249 | ||
Diary Inspection Reports |
5 | 250 | ||
Warren C. Heylman, Correspondence 1974-1977 |
5 | 251 | ||
Warren C. Heylman, Contract, Payments, COs |
5 | 252 | ||
AAA Construction Co., Correspondence 1975 |
5 | 253 | ||
Rejected Bids |
5 | 254 | ||
|
||||
Kamiak Apartments (Bldg. 660) |
||||
box | folder | |||
IDs for Handicapped Improvements |
5 | 255 | ||
Incinerators |
5 | 256 | ||
|
||||
Steptoe Family Housing (Bldg. 665) |
||||
box | folder | |||
Budget |
5 | 257 | ||
HUD Application |
5 | 258 | ||
Program |
5 | 259 | ||
General Correspondence 1972-1976 |
5 | 260 | ||
General Correspondence 1971 |
5 | 261 | ||
General Correspondence 1970 |
5 | 262 | ||
General Correspondence 1968-1969 |
5 | 263 | ||
Durham, Anderson, Freed Co., Correspondence, 7/72 |
5 | 264 | ||
Durham, Anderson, Freed Co., Correspondence, 1/71-6/72 |
5 | 265 | ||
Durham, Anderson, Freed Co., Correspondence, 7/70-12/70 |
5 | 266 | ||
Durham, Anderson, Freed Co., Correspondence, 1/70-6/70 |
5 | 267 | ||
Durham, Anderson, Freed Co., Correspondence 1968-1969 |
5 | 268 | ||
Durham, Anderson, Freed Co., Contract, Payments, COs |
5 | 269 | ||
Durham, Anderson, Freed Co., Progress Reports & Mtgs. |
6 | 270 | ||
Coordination Meeting Minutes, 1/70-7/70 |
6 | 270a | ||
Coordination Meeting Minutes, 7/70-10/70 |
6 | 270b | ||
Coordination Meeting Minutes, 11/70-7/71 |
6 | 270c | ||
Diary Inspection Reports, 8/17/71-6/14/72 |
6 | 271 | ||
Diary Inspection Reports, 1/71-8/16/71 |
6 | 272 | ||
Diary Inspection Reports, 11/69-12/70 |
6 | 273 | ||
Alfred Brown Co., Correspondence 1969-1973 |
6 | 274 | ||
Alfred Brown Co., Contract, Payments, COs |
6 | 275 | ||
Finish Schedule |
6 | 276 | ||
Pacific Testing Labs., Sub-Grade Investigation |
6 | 277 | ||
Pittsburgh Testing Labs., Concrete Testing |
6 | 278 | ||
Testing, Sound Tests |
6 | 279 | ||
Warren, Little & Lund, Inc., Correspondence 1969-1973 |
6 | 280 | ||
Warren, Little & Lund, Inc., Contract, Payments, COs |
6 | 281 | ||
Electric Smith, Inc., Correspondence 1969-1973 |
6 | 282 | ||
Electric Smith, Inc., Contract, Payments, COs |
6 | 283 | ||
Sprague's, Inc., Correspondence 1969-1973 |
6 | 284 | ||
Sprague's, Inc., Contract, Payments, COs |
6 | 285 | ||
Furnishings, Correspondence, 7/71-12/71 |
6 | 286 | ||
Furnishings, Correspondence, 1/70-6/71 |
6 | 287 | ||
Bon Marche (Furnishings), Contract, Payments, COs |
6 | 288 | ||
Hotpoint (Appliances), Contract, Payments, COs |
6 | 289 | ||
Serta Mattress Co., Contract, Payments, COs |
6 | 290 | ||
Spokane Dry Goods (Drapes), Contract, Payments, COs |
6 | 291 | ||
Richard Carothers Assoc., Correspondence 1969-1973 |
6 | 292 | ||
Sprague's, Inc., Damage Claim |
6 | 293 | ||
Rejected Bids, General |
6 | 294 | ||
Rejected Bids, Mechanical |
6 | 295 | ||
Rejected Bids, Electrical |
6 | 296 | ||
Rejected Bids, Landscaping |
6 | 297 | ||
Close-Out Problems |
6 | 298 | ||
Frozen Pipes |
6 | 299 | ||
Liquidated Damages |
6 | 300 | ||
|
||||
Graduate Student (McEachern) Residence Hall (Bldg. 805) |
||||
box | folder | |||
Budget |
7 | 301 | ||
DHUD Correspondence 1970-1973 |
7 | 302 | ||
Program |
7 | 303 | ||
General Correspondence 1972-1974 |
7 | 304 | ||
General Correspondence 1971 |
7 | 305 | ||
General Correspondence, 7/70-12/70 |
7 | 306 | ||
General Correspondence 1968-6/1970 |
7 | 307 | ||
Walker & McGough, Contract, Payments, COs |
7 | 308 | ||
Walker & McGough, Correspondence 1972-1973 |
7 | 309 | ||
Walker & McGough, Correspondence, 7/70-12/71 |
7 | 310 | ||
Walker & McGough, Correspondence 1968-6/1970 |
7 | 311 | ||
Walker & McGough, Contraction Meeting Minutes |
7 | 312 | ||
Diary Inspection Reports 1972 |
7 | 313 | ||
Diary Inspection Reports, 10/70-12/71 |
7 | 314 | ||
Skyline Construction Co., Correspondence 1970-1973 |
7 | 315 | ||
Skyline Construction Co., Contract, Payments, COs |
7 | 316 | ||
Skyline Construction Co., Liquidated Damages |
7 | 317 | ||
Finish Hardware |
7 | 318 | ||
Skyline Construction Co., Affirmative Action Reports |
7 | 319 | ||
Shannon & Wilson, Foundation Investigation |
7 | 320 | ||
Pittsburgh Testing Labs., Concrete Testing |
7 | 321 | ||
Arnold & Jeffers, Inc., Correspondence 1970-1973 |
7 | 322 | ||
Arnold & Jeffers, Inc., Contract, Payments, COs |
7 | 323 | ||
Arnold & Jeffers, Inc., Affirmative Action Reports |
7 | 324 | ||
Mechanical Guarantee Items 1972-1974 |
7 | 325 | ||
Maxwell's, Inc., Electrical, Correspondence 1970-1973 |
7 | 326 | ||
Maxwell's, Inc., Electrical, Contract, Payments, COs |
7 | 327 | ||
Maxwell's, Inc., Electrical, Affirmative Action Reports |
7 | 328 | ||
P&G General Contractors, Correspondence 1970-1972 |
7 | 329 | ||
P&G General Contractors, Contract, Payments, COs |
7 | 330 | ||
Furnishings, Correspondence 1969-1973 |
7 | 331 | ||
Walker & McGough, Furnishings, Contract, Payments, COs |
7 | 332 | ||
Spokane Dry Goods Co., Correspondence 1971-1972 |
7 | 333 | ||
Spokane Dry Goods Co., Contract, Payments, COs |
7 | 334 | ||
Rejected Bids, Mechanical |
7 | 335 | ||
Rejected Bids, Electrical |
7 | 336 | ||
Rejected Bids, Landscaping |
7 | 337 | ||
Rejected Bids, General |
7 | 338 | ||
Rejected Bids, Furnishings |
7 | 339 | ||
|
||||
Agricultural Sciences Bldg., Phs. I&II Lands. (Bl. 808) |
||||
box | folder | |||
Geolabs, Report on Foundation Investigation |
8 | 340 | ||
Correspondence 1971-1972 |
8 | 341 | ||
Lloyd J. Lovegren, Correspondence 1971-1973 |
8 | 342 | ||
Parsons Landscaping, Inc., Correspondence 1971-1972 |
8 | 343 | ||
Parsons Landscaping, Inc., Contract, Payments, COs |
8 | 344 | ||
Parsons Landscaping, Inc., Affirmative Action Reports |
8 | 345 | ||
Rejected Bids |
8 | 346 | ||
|
||||
Agricultural Sciences Bldg., Ph. II (Bldg. 808) |
||||
box | folder | |||
Budget |
8 | 347 | ||
Program |
8 | 348 | ||
General Correspondence, 7/70-1975 |
8 | 349 | ||
General Correspondence 1968-6/1970 |
8 | 350 | ||
Diary Inspection Reports |
8 | 351 | ||
Lloyd J. Lovegren, Correspondence, 7/70-1972 |
8 | 352 | ||
Lloyd J. Lovegren, Correspondence 1968-6/1970 |
8 | 353 | ||
Lloyd J. Lovegren, Contract, Payments, COs |
8 | 354 | ||
Lloyd J. Lovegren, Minutes of Construction Meetings |
8 | 355 | ||
Bouillon, Christofferson & Schairer, Rept. of Site Visit |
8 | 356 | ||
Vern W. Johnson & Sons, Correspondence 1970-1974 |
8 | 357 | ||
Vern W. Johnson & Sons, Contract, Payments, COs |
8 | 358 | ||
Vern W. Johnson & Sons, Affirmative Action Reports |
8 | 359 | ||
Keying Schedule |
8 | 360 | ||
Pittsburgh Testing Lab., Concrete Testing |
8 | 361 | ||
Arnold & Jeffers, Inc., Correspondence 1970-1971 |
8 | 362 | ||
Arnold & Jeffers, Inc., Contract, Payments, COs |
8 | 363 | ||
Arnold & Jeffers, Inc., Affirmative Action Reports |
8 | 364 | ||
Kehne-Crabtree Electric, Correspondence 1970-1972 |
8 | 365 | ||
Kehne-Crabtree Electric, Contract, Payments, COs |
8 | 366 | ||
Kehne-Crabtree Electric, Affirmative Action Reports |
8 | 367 | ||
Rejected Bids, General |
8 | 368 | ||
Rejected Bids, Electrical |
8 | 369 | ||
Rejected Bids, Mechanical |
8 | 370 | ||
|
||||
English Building (Bldg. 809) |
||||
box | folder | |||
Budget |
8 | 371 | ||
Foundation Investigation |
8 | 372 | ||
General Correspondence 1972-1975 |
8 | 373 | ||
Diary Inspection Reports |
8 | 374 | ||
Fred Bassetti & Co., Correspondence 1972-1974 |
8 | 375 | ||
Fred Bassetti & Co., Contract, Payments, COs |
8 | 376 | ||
Fred Bassetti & Co., Site Visit & Monthly Cons. Mtgs. |
8 | 377 | ||
Prime Construction Co., Correspondence 1971-1974 |
8 | 378 | ||
Prime Construction Co., Contract, Payments, COs |
8 | 379 | ||
Prime Construction Co., Affirmative Action Reports |
8 | 380 | ||
Pittsburgh Testing Labs., Concrete Testing |
8 | 381 | ||
Standard Plumbing & Heating, Correspondence 1971-1973 |
8 | 382 | ||
Standard Plumbing & Heating, Contract, Payments, COs |
8 | 383 | ||
Standard Plumbing & Heating, Affirmative Action Reports |
8 | 384 | ||
Kohler Electric, Correspondence 1971-1977 |
8 | 385 | ||
|
||||
Experiment Stations |
||||
box | folder | |||
Miscellaneous Correspondence 1973 |
9 | 386 | ||
|
||||
Sample Drying Building, Prosser |
||||
box | folder | |||
Budget |
9 | 387 | ||
General Correspondence 1971-1973 |
9 | 388 | ||
Paddock & Hollingbery, Correspondence 1971-1976 |
9 | 389 | ||
Paddock & Hollingbery, Contract, Payments, COs |
9 | 390 | ||
V.K. Powell & Co., Correspondence 1972-1973 |
9 | 391 | ||
V.K. Powell & Co., Contract, Payments, COs |
9 | 392 | ||
Rejected Bids |
9 | 393 | ||
|
||||
Feed Plant Facility, Prosser |
||||
box | folder | |||
Budget |
9 | 394 | ||
General Correspondence 1968-1971 |
9 | 395 | ||
Doulgas C. Durkoop, Correspondence 1970-1971 |
9 | 396 | ||
Douglas C. Durkoop, Contract, Payments, COs |
9 | 397 | ||
L&M Sales, Inc., Correspondence 1970-1971 |
9 | 398 | ||
L&M Sales, Inc., Contract, Payments, COs |
9 | 399 | ||
Rejected Bids |
9 | 400 | ||
|
||||
Horticulture Materials Storage Building, Prosser |
||||
box | folder | |||
Budget |
9 | 401 | ||
General Correspondence 1968-1970 |
9 | 402 | ||
Boyington & Read, General Correspondence 1968-1970 |
9 | 403 | ||
Boyington & Read, Contract, Payments, COs |
9 | 404 | ||
Burke Construction Co., Correspondence 1969 |
9 | 405 | ||
Burke Construction Co., Contract, Payments, COs |
9 | 406 | ||
Rejected Bids |
9 | 407 | ||
|
||||
Miscellaneous Small Projects |
||||
box | folder | |||
Boyington & Read, General Correspondence 1967-1968 |
9 | 408 | ||
|
||||
Machine Storage Building, Mt. Vernon |
||||
box | folder | |||
Budget |
9 | 409 | ||
General Correspondence 1968-1969 |
9 | 410 | ||
Henry Klein & Associates, Correspondence 1968-1969 |
9 | 411 | ||
Bustad, Inc., Correspondence 1969 |
9 | 412 | ||
Bustad, Inc., Contract, Payments, COs |
9 | 413 | ||
|
||||
Lab Remodeling, Mt. Vernon |
||||
box | folder | |||
Budget |
9 | 414 | ||
General Correspondence 1968-1969 |
9 | 415 | ||
Henry Klein & Associates, Correspondence 1969 |
9 | 416 | ||
Henry Klein & Associates, Contract, Payments, COs |
9 | 417 | ||
Gunderson Construction Co., Correspondence 1968-1969 |
9 | 418 | ||
Gunderson Construction Co., Contract, Payments, COs |
9 | 419 | ||
Rejected Bids |
9 | 420 | ||
|
||||
Dry Land Research Station, Lind |
||||
box | folder | |||
General Correspondence 1970-1971 |
9 | 421 | ||
General Correspondence 1961-1970 |
9 | 422 | ||
Douglas Durkoop, Correspondence 1970-1971 |
9 | 423 | ||
Douglas Durkoop, Contract, Payments, COs |
9 | 424 | ||
Appleby Construction Co., Correspondence 1970-1971 |
9 | 425 | ||
Appleby Construction Co., Contract, Payments, COs |
9 | 426 | ||
Rejected Bids |
9 | 427 | ||
|
||||
Coliseum Parking Structure |
||||
box | folder | |||
Budget |
9 | 428 | ||
General Correspondence 1970-1971 |
9 | 429 | ||
John Graham & Co., Correspondence 1970 |
9 | 430 | ||
John Graham & Co., Contract, Payments, COs |
9 | 431 | ||
Soils Investigation |
9 | 432 | ||
|
||||
Dog Runs |
||||
box | folder | |||
Budget |
9 | 433 | ||
General Correspondence 1968-1971 |
9 | 434 | ||
Daily Inspection Reports |
9 | 435 | ||
Culler, Gale, Martell, Ericson, Correspondence 1969-1977 |
9 | 436 | ||
Culler, Gale, et al, Contract, Payments, COs |
9 | 437 | ||
Twin City Construction, Correspondence 1970 |
9 | 438 | ||
Twin City Construction, Contract, Payments, COs |
9 | 439 | ||
Rejected Bids |
9 | 440 | ||
|
||||
East Campus Substation |
||||
box | folder | |||
Correspondence 1971-1972 |
9 | 441 | ||
|
||||
Troy Road Completion |
||||
box | folder | |||
Budget Estimates |
9 | 442 | ||
General Correspondence 1972-1973 |
9 | 443 | ||
L. Keith Hellstrom, Correspondence 1972-1973 |
9 | 444 | ||
L. Keith Hellstrom, Contract, Payments, COs |
9 | 445 | ||
C&S Builders, Inc., Correspondence 1972-1973 |
9 | 446 | ||
C&S Builders, Inc., Contract, Payments, COs |
9 | 447 | ||
Rejected Bids |
9 | 448 | ||
|
||||
Exterior Concrete Steps |
||||
box | folder | |||
General Correspondence 1965-1967 |
9 | 449 | ||
Carlson & James, Correspondence 1967 |
9 | 450 | ||
Jensen-Greene, Inc., Correspondence 1967 |
9 | 451 | ||
Jensen-Greene, Inc., Contract, Payments, COs |
9 | 452 | ||
Rejected Bids |
9 | 453 | ||
|
||||
Small Jobs |
||||
box | folder | |||
Carpenter Hall, General Correspondence 1967 |
9 | 454 | ||
Carlson & James, Contract, Payments, COs |
9 | 455 | ||
|
||||
Hourly Rate Contract |
||||
box | folder | |||
Douglas C. Durkoop, Correspondence 1969 |
9 | 456 | ||
Douglas C. Durkoop, Contract, Payments, COs |
9 | 457 | ||
|
||||
Miscellaneous Small Projects |
||||
box | folder | |||
Boyington & Read, Contract and COs |
9 | 458 | ||
|
||||
Mobile Home Project |
||||
box | folder | |||
Budget |
9 | 459 | ||
General Correspondence 1970-1971 |
9 | 460 | ||
Olson, Richert, Bignold, Correspondence 1970-1971 |
9 | 461 | ||
Olson, Richert, Bignold, Contract, Payments, COs |
9 | 462 | ||
|
||||
Wilson Mall (later called Terrell Mall) |
||||
box | folder | |||
Budget |
9 | 463 | ||
General Correspondence 1967-1973 |
9 | 464 | ||
Kenneth W. Brooks, Correspondence 1967-1973 |
9 | 465 | ||
Kenneth W. Brooks, Contract & COs |
9 | 466 | ||
C&S Builders, Correspondence 1968-1969 |
9 | 467 | ||
Rejected Bids |
9 | 468 | ||
|
||||